IREN Announces Monthly Investor Update for February 2024
This is a paid press release. Contact the press release distributor directly with any inquiries.

IREN Announces Monthly Investor Update for February 2024

Trade IREN on Coinbase
IREN
IREN

Figure 1

Expansion Schedule
Expansion Schedule · GlobeNewswire Inc.

Figure 2

IREN's Prince George NVIDIA H100 cluster
IREN's Prince George NVIDIA H100 cluster · GlobeNewswire Inc.

Figure 3

Childress Phase 1 (100 MW) construction progress
Childress Phase 1 (100 MW) construction progress · GlobeNewswire Inc.

Figure 4

Times Square, February 16, 2024
Times Square, February 16, 2024 · GlobeNewswire Inc.

SYDNEY, Australia, March 06, 2024 (GLOBE NEWSWIRE) -- IREN (Iris Energy Limited) (NASDAQ: IREN) (together with its subsidiaries, “IREN” or “the Company”), a leading next-generation data center business powering the future of Bitcoin, AI and beyond, today published a monthly investor update for February 2024.

Key Highlights

Bitcoin Mining

AI Cloud Services

  • 310 Bitcoin mined in February

  • Record operating hashrate of 7 EH/s

  • 20 EH/s expansion in 2024

  • Contract signed with poolside AI

  • Expansion to 816 NVIDIA H100 GPUs

Data Centers

Corporate

  • Expanding to 460MW in 2024

  • Rebrand from Iris Energy to IREN

  • Second quarter results released

Key Metrics

Bitcoin Mining1

Feb-24

Jan-24

Dec-23

Average operating hashrate (PH/s)

6,299

5,642

5,576

Renewable energy usage (MW)2

174

163

161

Bitcoin mined

310

341

399

Mining revenue (US$'000)

15,212

14,466

17,174

Electricity costs (US$'000)3

6,241

6,376

5,926

Revenue per Bitcoin (US$)

49,134

42,436

43,056

Electricity cost per Bitcoin (US$)

20,158

18,705

14,858


Bitcoin Mining

February operations

  • Operating hashrate increased to 7 EH/s (Feb 29, 2024)

  • Monthly mining revenue increased to $15.2m primarily due to higher average hashrate of 6.3 EH/s and higher Bitcoin price of $49.1k

Expansion to 20 EH/s in 2024

  • H1 2024 (10 EH/s) - 7 EH/s installed, remaining 3 EH/s to be commissioned

  • H2 2024 (20 EH/s) - 10 EH/s of new miners secured via fixed price contracts4, single site expansion at Childress

Expansion Schedule
Expansion Schedule


AI Cloud Services

GPU cloud service contract signed

  • Contract secured with leading AI company, poolside, following rigorous customer testing requirements

  • Initial 3-month term and extension option for an additional 3-months at the customer's election

  • Additional customer conversations ongoing

Tripling AI cloud services business

  • Fast-tracking AI cloud services business to 816 NVIDIA H100 GPUs with the purchase of 568 additional GPUs

  • Delivery and commissioning of additional GPUs expected during Q2 2024

  • Financing workstreams underway to support growth

IREN's Prince George NVIDIA H100 cluster
IREN's Prince George NVIDIA H100 cluster


IREN's Prince George NVIDIA H100 cluster

Data Centers

Construction update

  • Childress Phase 1 (first 100MW)

    • Supports expansion to 10 EH/s in H1 2024

    • 60MW energized, 40MW to be commissioned in the coming months

  • Childress Phases 2 & 3 (next 200MW)

    • Supports expansion to 20 EH/s in H2 2024

    • Site civils & procurement underway. Phase 2 substation construction to commence this month

Childress Phase 1 (100 MW) construction progress
Childress Phase 1 (100 MW) construction progress


Childress Phase 1 (100 MW) construction progress

Data Center

Capacity
(MW)

Capacity
(EH/s) 5

Timing

Status

Canal Flats (BC, Canada)

30

0.8

Complete

Operating

Mackenzie (BC, Canada)

80

2.6

Complete

Operating

Prince George (BC, Canada)

50

1.6

Complete

Operating

Childress Phase 1 (Texas, USA)

60

2.0

Complete

Operating

Total Operating

220

7.0

 

 

Childress Phase 1 (Texas, USA)

40

3.06

H1 2024

Under construction

Childress Phase 2-3 (Texas USA)

200

10.07

H2 2024

Under construction

Total Operating & Construction

460

20.0

 

 

Childress Phase 4-6 (Texas, USA)

300

 

TBD

Power available

Development Site (Texas, USA)

1,400

 

Late 2026

Connection underway

Total Capacity

2,160

 

 

 